Recent Daily Logs
View All
2025-10-30
Phoenix Office Complex
14 workers · 112h
Foundation concrete pour completed. 320 cubic yards poured. ...
2025-10-30
São Paulo Residential Tower
10 workers · 80h
Site preparation delayed by morning rain. Drainage system in...
2025-10-29
Riyadh Metro Station North
18 workers · 144h
Metro tunnel boring progressing well. Reached 45m depth. Coo...
2025-10-28
Phoenix Office Complex
12 workers · 96h
Rebar cage installation 60% complete. Concrete delivery sche...
2025-10-27
Phoenix Office Complex
15 workers · 120h
Completed foundation excavation. Ready for rebar installatio...
Recent Messages
View All
Wei Chen
2025-10-30 16:35:13
Electrical conduit installation 70% complete. Should finish by end of week.
Phoenix Office Complex
Ahmad Al-Rashid
2025-10-30 15:35:13
Steel crew checking in. Metro tunnel is progressing ahead of schedule. Great tea...
Riyadh Metro Station North
Site Manager
2025-10-30 14:35:13
Excellent work on the foundation prep. Quality control gave us the green light. ...
Phoenix Office Complex
Jose Rodriguez
2025-10-30 12:50:13
Got it, foreman. Concrete mixer is ready and inspected.
Phoenix Office Complex
Carlos Martinez
2025-10-30 12:35:13
Team, foundation pour starts at 6 AM sharp tomorrow. Everyone needs to be here b...
Phoenix Office Complex