2025-10-26 —
Project: Phoenix Office Complex
Weather: Partly cloudy, 78°F • Workers: 14 • Hours: 112
Foundation concrete pour completed. 320 cubic yards poured. Excellent weather conditions. Quality control tests passed.
2025-10-26 —
Project: São Paulo Residential Tower
Weather: Rain showers, 72°F • Workers: 10 • Hours: 80
Site preparation delayed by morning rain. Drainage system installation in progress. Weather forecast better for tomorrow.
2025-10-25 —
Project: Riyadh Metro Station North
Weather: Hot, 102°F • Workers: 18 • Hours: 144
Metro tunnel boring progressing well. Reached 45m depth. Cooling breaks every 2 hours due to heat.
2025-10-24 —
Project: Phoenix Office Complex
Weather: Clear, 82°F • Workers: 12 • Hours: 96
Rebar cage installation 60% complete. Concrete delivery scheduled for tomorrow 6 AM. All safety protocols followed.
2025-10-23 —
Project: Phoenix Office Complex
Weather: Sunny, 85°F • Workers: 15 • Hours: 120
Completed foundation excavation. Ready for rebar installation tomorrow. Excellent progress, ahead of schedule.